The major case studies take up most of the space on this site, but most of KBT's work consists of the many bridges, underpasses, decks and facilities where the membrane was applied, measured and covered over without anyone writing about it. Here is a selection of 44 of our 100+ projects in Scandinavia, with a focus on the period since 2016: from a tunnel beneath track ballast in Copenhagen to a steel deck on a suspension bridge in northern Norway.

100+Projects in Scandinavia; a selection of 44 is shown here
2016–2026Carried out year after year, summer and winter
DK + NODenmark and Norway
98,000 m²Largest single project (Storstrøm Bridge)
Road bridgesRailway and underpassesTunnelsCar park decks and buildingsTanks and facilities

Road bridges

ProjectYearScopeClient
Storstrøm Bridge (Storstrømsbroen)CASE2022–202698,000 m² of membrane on the road, railway, emergency walkways and cycle path + 15,000 m² of Decseal wearing courseDanish Road Directorate (Vejdirektoratet)
Kronprins Frederik Bridge (Kronprins Frederiks Bro)CASE (in Danish)2026752.6 m² of re-waterproofing of the steel deck on a bascule bridge (type Vb)Danish Road Directorate (Vejdirektoratet)
Hålogaland Bridge (Hålogalandsbroen), Narvik (Norway)2018Steel deck on a suspension bridge: Eliminator on the steel joints and an additional layer on the factory-applied membrane, plus Bond Coat No. 3 on the entire deck (approx. 15,300 m²) beneath mastic asphaltStatens vegvesen (Norwegian Public Roads Administration)
Old Little Belt Bridge (Gl. Lillebæltsbro)CASE (in Danish)2018–20197,000 m² refurbishment with membrane on a concrete deckDanish Road Directorate (Vejdirektoratet)
Oddesund Bridge (Oddesundbroen)20163,500 m² of membrane beneath asphalt, carried out in phases under trafficDanish Road Directorate (Vejdirektoratet)
Aggersund Bridge (Aggersundbroen)20161,250 m² of membrane beneath asphaltDanish Road Directorate (Vejdirektoratet)
Inner Harbour Bridge (Inderhavnsbroen), Copenhagen2026Refurbishment of the cycle path and edge beam: membrane, Decseal wearing course and barrier boxes, carried out at nightMunicipality of Copenhagen
Langebro, Copenhagen2020Membrane on the bridge deck–
Skovdiget Østbro, Bagsværd20214,000 m² of membrane, carried out in phases–
Thurø Bridge (Thurøbroen)2020Membrane on the bridge deck–
Vindinggård Ringvej, Vejle2020Three bridges–
Bridge 004, Odense2017Road bridge, 305 m² in a single dayMunicipality of Odense
Gl. Århusvej, HorsensCASE (in Danish)2017Approx. 600 m² of re-waterproofing of an existing bridge in two phases–
Bridge 25, Østerstationsvej, Odense2017Membrane on a bridge, carried out in DecemberMunicipality of Odense
Åkær Å, E20 near Lunderskov2017Motorway bridge, carried out in February under a heated tent–
Give and Brande2017Two road bridges–
Salbyvej and Sonnerupvej2018Road bridges–
Bistrupvej, Farum2018Approx. 200 m² of membrane on a bridge–
Greve, bridge 622021Membrane on a bridge–
Horsensvej, Vejle2016125 m² in four phases, carried out in November under a tent–
Huul Mølle and Jordmodervej, Nibe2016Two bridges on the same day–
Vejen2016Two smaller bridges, carried out in November–

Railway and underpasses

ProjectYearScopeClient
Ringsted–Femern railway line, six underpassesCASE (in Danish)2020Over 1,700 m² on underpasses and wildlife crossingsBanedanmark (Danish rail infrastructure manager)
Ringsted–Femern railway line, road and railway bridges2017–20184 road bridges (2,000 m²) and 11 railway bridges (1,500 m²) beneath ballastBanedanmark
Railway bridge, Hedehusene2025Membrane and thin waterproofing on the deck and walls, carried out in two phases and holiday testedBanedanmark
Bridge 20998, Viborgvej, Randers2018Approx. 1,650 m² road bridge over the railway, carried out in four phases from June to DecemberBanedanmark
Ny Ellebjerg StationCASE (in Danish)2019Approx. 1,450 m² tunnel/underpass, carried out January–March, with protective concrete and ballast on topMetroselskabet (Copenhagen Metro)
Orevej underpass2019Membrane on an underpass–
Orehoved, underpass2019500 m² trial area ahead of Storstrøm Bridge–
Slagelse Station2021Membrane on the station structure–

Tunnels and path tunnels

ProjectYearScopeClient
Fehmarnbelt Fixed Link (Femern-forbindelsen), tunnel elementsCASE (in Danish)202560,000 m² of waterproofing on STE tunnel elementsFemern A/S
Path tunnels, Esbjerg and Gjesing2020Membrane on path tunnels–

Car park decks and buildings

Read how we refurbish car park decks and rooftop car parks while they remain in use (in Danish).

ProjectYearScopeClient
Danske Bank headquarters (Danske Bank Domicil), PostbyenCASE (in Danish)2019–2022Preprufe beneath the base slab and Type V on the podium deckDanica Pension
Postbyen, phase 22021Membrane on base slabs, lift pits and walls–
Glostrup Shopping Center, rooftop car parkCASE (in Danish)2024–2025Approx. 5,900 m² refurbishment of the rooftop car park above the shops, carried out in phases while in operation–
Museum of Danish Resistance (Frihedsmuseet), Copenhagen2018–2019Approx. 1,050 m² deck above the museum, carried out in winter 2018–19–
Køge multi-storey car park (P-hus Køge)2017–2020Membrane on car park decks–
Oslo Plads, Copenhagen2021Membrane on a deck–
Hotel roof terrace2021Membrane on a roof terrace–
Copenhagen Airport (Københavns Lufthavn)2017Membrane on an airport structure–
Terrace above a pool, private villaCASE (in Danish)2026130 m² concrete terrace above an indoor pool, holiday tested at 12 kVPrivate

Tanks and technical facilities

ProjectYearScopeClient
HOFOR Gevninge Waterworks (HOFOR Vandværk Gevninge)CASE (in Danish)2023584 m² on recycled-water tanks in two daysHOFOR
Silo, Nordhavn2020Spray-applied membrane on a silo structure, carried out in December–
Process tank, industrial facility2017Membrane on a tank–
This list is a selection and is updated on an ongoing basis. Projects from 2016–2020 were carried out under the name Kemitura Bro & Tunnel AS, the predecessor of KBT Waterproofing. The client is stated only where it is a public client or is named in a published case study; other references are available on request. Documentation from individual projects belongs to the client and is not released.
Do you have a project similar to one of these? Contact KBT →

Contact us for a technical assessment

Whether it is a new bridge, an existing tunnel or a car park deck, describe the structure and we will get back to you within one working day. We answer in English, Danish and Norwegian.

Write to us directly and a specialist will reply, not a system. The email opens with the information we need, so you get a useful answer quickly.

Send an email →

Or call: +45 47 17 18 55  · 

We do not use contact forms. Your email is handled as described in our privacy policy (in Danish).